0193- 25 Year Old Pump

Industry: Water / Wastewater / Desalination
Problem: Corrosion / Erosion, Safety Surfacing
Project Goal: Repair and Protection
Location: United States
Status: Completed
Products Used: CeramAlloy CP+AC used for Rebuilt, CeramAlloy CL+AC used for Protection
Project Description

Located at a wastewater treatment facility, this impeller from a 25 year old pump was headed to the scrap yard. 

Replacement parts for the pump were obsolete and the city was considering replacing the pump for $12,000+ and 8 weeks of downtime. After grit blasting the impeller and minimal welding, the veins were rebuilt with CeramAlloy CP+AC.

Followed by 2 coats of CeramAlloy CL+AC.

This repair and protection application only took 1 week to complete and the total cost for material and labor was less than $4,000. Problem Solved!

 